Tianjin Economic and Technological Development Zone sewage treatment plant is to improve the investment environment and the establishment of environmental protection infrastructure projects, the sewage pump room was built in the former is known as salt Wang Zi sea sedimentation tank, about 2m below the surface of the earth fill for soil, and then All of them are sediment-shaped flow-like silt for many years. The underground pumping station of the pumping station has a depth of 13m and a convex shape. Due to the arrangement of substations, dehumidifier rooms and mud cake storage areas nearby, it is not possible to adopt the open-cut foundation pit or deep foundation maintenance structure, which is designed as a polygonal caisson structure. It is very difficult to control the speed and direction of caisson sinking, so it has not yet been solved so far Construction problems. In accordance with the design intent, the three stations of the 18th Bureau of China Railway Construction contracting for this project are to prefabricate the DJM piles at the foot of the sink shaft to form a continuous diaphragm pylon underground continuous wall. For the shaft wall of the sunk shaft, Supporting the wall, the process of sunk well sinking in the silt becomes a controllable process and successfully solves this construction problem. 1 Construction Preparation 1.1 Excavation and filling to reduce the initial elevation According to the geological conditions of caisson parts, in order to ensure the sinking of the sinking stage of the equilibrium subsidence, the artificial fill layer is excavated, the caisson precast and the initial elevation set Is 0.48m, thus creating two favorable conditions: one is due to the initial settlement of the silt, its water content and bearing capacity uniform, easy to calm; second, the total settlement of caisson down 2.5m, the upper third Section 0.5m thick caisson can not be used as caisson construction, but after pouring caisson back cover, so that not only reduces the caisson weight (still able to meet the sinking weight requirements), but also shorten the sinking depth, serve two purposes. 1.2 DJM pile construction powder spray pile, reinforcing the soft soil under the sinkhole edge so that the sinkhole in the continuous powder cement pile formed by the continuous diaphragm wall sinking. DJM construction should pay attention to the following points: ① The position should be accurate, the outer edge of the pile along the outer edge of the line tangent shall not be exposed, so as not to sink caisson cement soil squeeze to the outside of the shaft, the loss of support. ② pile bottom should be deep caisson edge design elevation 16m. ③ outer ring pile at the end of the foot and the pile top 1.0m range of cement 10% (according to the weight of the pile), the remaining pile 7%. ④ The inner circle pile cement volume is 10%. ⑤ inner and outer two rows of piles spacing 10cm, in order to ensure excavation of the inner side of the pile does not hurt outside the pile. 2 caisson prefabrication 2.1 prefabricated site layout As the caisson shaft wall is built together pump wall pool, so choose the pump pool position for caisson prefabricated position. In order to facilitate the construction and consider the need of concrete pouring in the caisson support wall, the surface of the soft soil in the site is compacted with 15cm and 8% lime soil, and the bottom of the support wall is made another 10 limestone platform. 2.2 Prefabrication The original design of the open caisson is three sections. After the topsoil is dug, the elevation of the ground is exactly the top elevation of the second section of the caisson. Therefore, the third section of caisson is no longer regarded as the caisson structure, while the two sections of caisson Shen then place the back cover then hit. In order to reduce the weight of the first pouring concrete, to avoid excessive sinking and uneven settlement caused by concrete cracking, the first section of concrete pouring completed in two, the first casting edge (pouring 1.0m) until the concrete strength to design strength Over 70%, pour the remaining part and construct the second section in turn. Two sinkholes concrete all completed, a sink in place. 2.3 Bladed bottom die and bottom die support wall According to the preliminary design, two rows of powder spray pile reinforce the soft soil layer. The original ground is muddy clay, the allowable bearing capacity is 80kPa, the cement content is 10%, the unconfined compressive strength is up to 600kPa for 7d, and the compressive strength is up to 800 ~ 1000kPa for 28d. The total amount of caisson concrete is 444m3. According to the capacity of 2.5t / m3, the total weight is 3610t. The sinkhole bottom area is 44.88m2. Therefore, when the sole surface of the blade edge is used as the support surface, the bearing load is 804 kPa. Based on the above calculation, and taking into account the error of DJM construction, the sinking edge is placed on the top of DJM pile and the bearing capacity can not fully meet the requirements. However, during the precasting process of sinking well, Support bottom wall to increase support bottom mold to share the weight of part of caisson. 3 Sunk Well Sinking 3.1 Preparation The sunk well must begin to sink after the concrete strength has reached the design strength. Make the following preparations before sinking: ① Marking marks on the wall of the sunk well, set the standard observation points at the four corners of the sunk well, The amount and balance of the situation; set a vertical line at the central axis to observe the caisson displacement and balance. ② remove the module. ③ Excavation of the surface of the bottom of the lime-soil support wall demolition, caisson slightly subsidence, but then the edge of the blade edge bearing capacity, caisson stop. 3.2 Subsidence coefficient calculation The subsidence factor formula: K = Q / (f · h · L)> 1 (1) where Q - gravity causation gravity  f - coefficient of friction, 11.76 kN / m2 h  - Maximum sinking depth L  - The maximum friction coefficient of the perimeter of the caisson outside of the caisson is taken as the maximum value of the soft caisson. The sinking coefficient of the gravity caisson of the general structure can still reach 3.0, not to mention the silt No lag The problem is that when the sinking depth reaches the requirement, it will still sink more than that, so control measures must be taken. 3.3 DJM piles continuous wall control mechanism of sinking ① guide and prevent sudden sinking, flood According to the preliminary design concept, in the borehole density range, under the edge of the blade, pre-playing two rows of DJM pile strata to prevent caisson Sudden sinking, settling too fast and a comprehensive measure of infiltration, the role of the principle is as follows: First, the powder spray pile to form a continuous wall of cement land, for the caisson is a closed clip in the silt in the load-bearing wall The sinking process of the whole sinkhole is also the excavation process of this bearing wall, so that the sinking speed and the smoothness of the sinkhole can be completely controlled by manually removing the powder jetting pile. Second, the implementation of open caisson in silty soft soil, in the process of digging soil subsidence prone to flooding, that is, flow-shaped plastic silo outside the well due to large differences in soil surface when the instability and slippery , Sliding arc edge into the hole at the foot of the foothole, so that the hole is only unearthed but the soil elevation does not drop, and the soil elevation subsidence, easily lead to uneven soil pressure, resulting caisson inclination. Pre-beating the blade at the foot of the first two laps spray pile, forming a 1.2m thick cement soil wall to prevent the formation of soil outside the shaft wall sliding inrush into the wall. (2) Controlling the design depth of caisson sinking When the caisson sinks to the design elevation and the soil below the bottom of blade edge is still silt, it can be known from the subsidence coefficient that the carrying capacity of the silt is not enough and will sink more than the designed depth At the foot of the next prefabricated powder spray pile underground continuous wall, can make the bottom surface sinkhole to the design elevation, fell on the DJM pile diaphragm wall underground surface to solve the problem of control caisson sinking depth. When sinking needs sinking,

Rivets

Rivets

Rivets are a permanent mechanical fastener. Before being installed a rivet consists of a smooth cylindrical shaft with a head on one end. The end opposite the head is called the buck-tail. On installation the rivet is placed in a punched or drilled hole, and the tail is upset, or bucked (i.e., deformed), so that it expands to about 1.5 times the original shaft diameter, holding the rivet in place.

Rivets Categories:
About Rivets,it is also belong to connecting and fastening,
Normally it can be divided into several categories:Solid Rivets,Rivet Nuts,Blind Rivets and so on.
And our Non-standard Rivets can be produce according to drawings and samples.

We have ability to control the quality during production before sending to customers. We wish to do your best supplier of Rivets in China..


Rivets Purpose:
We are manufacture to supply our Rivets to our customers,We Have responsibility to give our best goods with good quality . So we will track all step to customers at all times. such as: products requirement,Technology and property ,package,shipment ,and files ,and sales serve,

Welcome all of you to contact with us,we promise to give our the best We are improving as your supporting.

Rivets are a permanent mechanical fastener. Before being installed a rivet consists of a smooth cylindrical shaft with a head on one end. The end opposite the head is called the buck-tail. On installation the rivet is placed in a punched or drilled hole, and the tail is upset, or bucked (i.e., deformed), so that it expands to about 1.5 times the original shaft diameter, holding the rivet in place.

Rivets Categories:
About Rivets,it is also belong to connecting and fastening,
Normally it can be divided into several categories:Solid Rivets,Rivet Nuts,Blind Rivets and so on.
And our Non-standard Rivets can be produce according to drawings and samples.

We have ability to control the quality during production before sending to customers. We wish to do your best supplier of Rivets in China..


Rivets Purpose:
We are manufacture to supply our Rivets to our customers,We Have responsibility to give our best goods with good quality . So we will track all step to customers at all times. such as: products requirement,Technology and property ,package,shipment ,and files ,and sales serve,

Welcome all of you to contact with us,we promise to give our the best We are improving as your supporting.

Rivets,DIN124 Steel Round Head Rivet,Solid Rivet fastener Zinc plated

Suzhou Gubao Screws Co.,Ltd. , https://www.hongyiscrew.com

Posted on