The firefighting project has entered the stage of full-scale linkage debugging and is about to undergo fire acceptance. In order to ensure that the acceptance of fire protection can be passed successfully, the relevant units shall be coordinated to do the following:
First, the electromechanical construction unit should be completed before the fire linkage debugging:
1 , carry out load test and cooperate with fire control linkage test for all fire electrical equipment body.
2, double check all terminal boxes dual power switching power supply is normal in the power generator state.
3 , with the relevant companies to carry out the fire pump and spray pump simulation failure status of the standby pump automatically put into the test.
4, with the related companies were resected non-fire control to start the test and fire power emergency lighting.
5, the exhaust fan inlet damper 280 ℃ the fan is shut off to stop the test operation. Manually opening the exhaust valve should automatically start the exhaust fan test.
6, each end of the exhaust port and check the pressure wind blower port, should meet fire code requirements. Check that the relevant smoke damper valve is closed in the alarm state.
7, the alarm check whether the air conditioner to stop running region, air moving machine is stopped.
8. Test the grounding resistance of the dedicated grounding board for the fire control center and the fire pump room , respectively, and meet the fire code requirements. And provide test records for future reference.
9, automatic operation and manual inspection of fire in the elevator bottom drain.
10, the mounting position and the number of inspection and emergency lighting evacuation signs meets fire code requirements.
11, when testing electricity cut off standby generator in operation meets the requirements of the time.
12, a standby generator forced to start testing and full load running test.
13, should be normal fire radio system in use, the installation position of the speaker volume and meets the requirements, the capacity of the standby power amplifier meets the requirements. Check whether the fire radio can normally enter from the background music status during the fire alarm. Check whether the fire broadcast manual selection play meets the specification requirements.
Second, water supply and drainage and fire water construction units should be completed during the fire-fighting linkage debugging:
1. Check the roof and basement fire water tank whether the requirement stocked with water, and the automatic replenishment system is functioning. Whether the replenishment time meets the specification requirements.
2, fire pump room and alarm check valve at the end of each spray pipe network drainage means drainage and fire at the elevator shaft at the channel if in use. And whether the displacement meets the specification requirements.
3, each spray pipe water distribution network in the means at the end of the drainage valve and the alarm, check the operation of the flow switch is normal, the water alarm starts to sound the alarm time after the respective drainage valve is normal.
4 , the outdoor pipe network pressure test qualified and put into use, municipal two-way water supply access and should be put into use. Check if the valve at each key point is open.
5, indoor and outdoor fire hydrant system and fire hydrant pipe network installation, pressure test and put into use. Check whether the water column of the fire hydrant test shot at the most unfavorable point meets the specification requirements.
6 , spray regulator system pipe network and equipment installed, test pressure qualified and put into use. Check whether the pressure of the stabilized pipe network meets the requirements of quick alarm and pump start.
7 , spray pump adapter and fire hydrant pump adapter and its pipe network installation, test pressure qualified and put into use. Manually simulate the hose access of the fire truck and confirm the non-return effect and water pressure of the water pump coupling.
8, fire pumps and spray pumps and diesel pump and pipe network installation, pressure test and put into use, and the pump operating pressure and flow tested to meet the requirements.
9, test rooftop water tanks and fire water in the basement of the largest domestic water consumption, water consumption can still meet the requirements of the fire. Check the status of the liquid level display device.
Third, the elevator construction unit should be completed during the fire-fighting linkage debugging:
1, the elevator installation is completed and the acceptance of the technology by oversight bodies.
2, testing the fire inside the elevator car and the fire control center telephone communications.
3, test fire elevator the first floor landing Fireman button manual control of the elevator, the elevator operating state checking elevator landing comply with the requirements.
4, simulation testing by an elevator operating state of the fire control signal.
Fourth, fire shutter construction units should be completed before the fire linkage debugging:
1, a control site manual shutter button body test run should be normal, normal sound and light alarm.
2 , fire partition smoke curtain smoke, temperature detector simulation trigger a forced drop curtain test should meet the specification requirements.
3, check the garage (evacuation) roll on both sides of the blind channels are arranged whether the manual button, with the temperature sensitive smoke alarm sound and light.
4, the check roller blind landing ground clearance meets the requirements.
5 , simulate the test fire shutter is controlled by the fire signal when the work status.
5. Each construction unit of the gas fire protection zone shall be completed before the fire-fighting linkage debugging:
1 , gas extinguishing bottle group and pipe network installed, and pressure test qualified.
2 , send exhaust system and damper work properly.
3 , diesel engine group simulation emergency stop control is normal.
Sixth, the civil construction unit should be completed before the acceptance of fire protection:
1, and a lane width is set to check the fire road, the height requirements for compliance.
2, check all evacuation routes, and the width of staircases provided for compliance requirements.
3, check all floors, wells, whether the firewall holes all in compliance with fire blocking material requirements.
4. Check that all fire doors opening direction is correct.
7. The construction party shall complete before the acceptance of fire protection:
1 , Fire Control Center set " 119 " direct access to the outside line.
2, each of the equipment room, according to specifications provided in public places portable fire extinguisher.
3, the central fire control, fire pump room, equipment room main, gas fire protection zones disposed permanent signs.
4 , to provide fire inspection meeting room.
VIII. All relevant units shall prepare before the acceptance of fire protection:
1, organize and collect fire pump, pump adapter, the shower head; fire doors and fire shutter; fire box and with water, gun, then buckle; fire alarm equipment, fire radio, emergency evacuation signs linkage cabinet, emergency lighting Cabinets and lamps; gas fire extinguishing equipment; smoke prevention fans, fire dampers; proof of supply of fire extinguishers such as portable fire extinguishers.
2, collate and collect fire pump and pipe network, fire extinction system tied to the pipe network, water pressure test records sprinkler pipe network equipment regulator (supervising engineer should have signature).
3, collection and sorting systems and fire related electrical, plumbing FIG completed; and fire hydrant system built drawings; fire pump room and the center position of the fire control plane built drawings; construction general plane completion FIG.
4, the preparation of the project profiles for reference when the fire system Fire Department inspection.
5, the preparation of fire inspection organization plan, acceptance plan routes and programs for reference when Fire Department inspection. (see attached)
6, collate and collect relevant information at the time of the fire built, especially the previous audit opinion the fire, when the fire department for acceptance see.
7, collection design qualification certificates (stamped copy).
8, qualified fire smoke collection systems, elevators, fire shutter, fire doors, fire extinguishing gas and other construction units of your company documents (copy of the seal). For review by the fire station.
9 , fire maintenance contract (agreement).
10, Test Report: Report of fire detection, electrical detection report. (Supervisor evaluation report).
The information in this article comes from the Internet and was reorganized and edited by China Rescue Equipment Network.
Cut rounded holes in wood, plastic, PVC and ABS with this Hole Saw set! Made of heat treated 45 carbon steel this hole saw kit can easily withstand the rigors of cutting circles in wood, plasterboard or drywall. Features include a black oxide finish to prevent rust and pilot bit with a 135 degree split point for fast, With this powerful hole saw set, you`ll be able to drill large diameter holes quickly and efficiently.
Bi-Metal Hole Saw,Bi-Metal Cutting Tool,Hole Saw Set Bi-Metal,Constant Hole Saw
Behappy Crafts (suzhou)Co.,Ltd , https://www.jshaoyue.com